Home / gate / Updates / 983521769

Updated: Question in GATE 2012 Production and Industrial Engineering Paper with Solution

August 09, 2012

A question in GATE 2012 Production and Industrial Engineering Paper with Solution has been updated:

A process needs to be standardized for method and time. Which one of the following represents the sequence of work study experiments?

  1. Only time study
  2. Time study and method study simultaneously
  3. Method study followed by time study
  4. Time study followed by method study